April 29 – June 1 Look ahead

Saturday &  Sunday

NIGHT WORK: 10 PM – 5 AM SHIFTS

Set-up lane closures at 10pm.  Minor utility street work along Congress, lanes will re-open each morning.

 

Monday, 4/30 through Friday, 6/1 – 

7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include Structural Steel and metal decking in garage levels.


April 20 – April 22 Tower crane install & congress lane closure

Friday, 4/20 – Sunday, 4/22 –

LANE CLOSURE – Friday at Midnight – Sunday at Midnight.

Work includes the delivery and installation of our tower crane.  During this time the 2 East bound lanes will be closed.  Traffic on congress will be reduced to 1 lane in each direction.


FEBRUARY 19 – march 2 LOOK AHEAD

Monday, 2/19 through Friday, 3/2 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Excavation and removal of soil from site to be completed. Additional work to include mud mat and foundation slab pours.


OCTOBER 29 – november 3 LOOK AHEAD

Sunday, 10/29 through Thursday, 11/02 – 

NIGHT WORK: 9 PM – 5 AM SHIFTS

Set-up lane closures at 9pm. Minor utility street work along Congress, lanes will re-open each morning.

 

Monday, 10/30 through Friday, 11/03 – 

7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include removing guide walls and demoing slurry wall tops.

 


October 15 – October 20 look ahead

Sunday, 10/15 through Thursday, 10/19 – 

NIGHT WORK: 9 PM – 5 AM SHIFTS

Set-up lane closures at 9pm. Minor utility street work along Congress, lanes will re-open each morning.

 

Monday, 10/16 through Friday, 10/20 – 

7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include fabrication of rebar cages and installation of slurry panels below grade.

 


AUGUST 28 – SEPTEMBER 8 LOOK AHEAD

7:00AM TO 3:30PM SHIFTS   

Monday, 8/28 through Friday, 9/8 – 

All work will be completed onsite.  Work to include fabrication of rebar cages and installation of slurry panels below grade.