October 25 – December 21 look ahead

Thursday, 10/25 through Thursday, 12/20 – 

NIGHT WORK: M-TH – 9 PM TO 5 AM SHIFTS

Set-up lane closures at 9pm.  Work to include the installation of the buildings sewer line along Congress.  Lanes will re-open each morning.

 

Thursday, 10/25 through Friday 12/21 – 

1ST SHIFT: M-F – 7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include structural steel, metal decking, concrete pours, interior detail work and window installation.

 

Thursday, 10/25 through Thursday 12/20 – 

2ND SHIFT: M-TH – 4:00PM TO 2:00AM SHIFTS 

All work will be completed onsite. Work to include the delivery and installation of precast panels.

Tags: Lookahead

July 2 – Sepmtember 31 Look ahead

Monday, 7/2 through Friday, 8/31

7:00AM TO 3:30PM SHIFTS 

Intermittent utility work in manholes on I-90 off ramp.  Remainder of work will be completed onsite.  Work to include Structural Steel, metal decking, concrete pours and interior detail work.

*No work on Wednesday, July 4th.

Tags: Lookahead

April 20 – April 22 Tower crane install & congress lane closure

Friday, 4/20 – Sunday, 4/22 –

LANE CLOSURE – Friday at Midnight – Sunday at Midnight.

Work includes the delivery and installation of our tower crane.  During this time the 2 East bound lanes will be closed.  Traffic on congress will be reduced to 1 lane in each direction.


march 25 – april 19 look ahead

Sunday, 3/25 through Thursday, 4/19 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Rebar and plumbing placement ongoing.  Additional work to include concrete back-fill, site work and bracing removal.

 

Tags: Lookahead

March 5 – March 16 Look ahead

Monday, 3/5 through Friday, 3/16 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Rebar and plumbing placement ongoing.  Additional work to include mud mat and foundation slab pours.

Tags: Lookahead

FEBRUARY 19 – march 2 LOOK AHEAD

Monday, 2/19 through Friday, 3/2 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Excavation and removal of soil from site to be completed. Additional work to include mud mat and foundation slab pours.


February 5 – February 16 Look ahead

Monday, 2/5 through Friday, 2/16 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Excavation and removal of soil from site to be completed. Additional work to include mud mat and foundation slab pours.

Tags: Lookahead

December 11 – January 12 look ahead

Monday, 12/11 through Friday, 1/12 – 

7:00AM TO 3:30PM SHIFTS

All work will be completed onsite.  Work to include installing cross bracing, form-work at cap beams and removal of soil from site.

Tags: Lookahead

november 27 – december 8 lookahead

Monday, 11/27 through Friday, 12/8 – 

7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include installing cross bracing, formwork at cap beams and removal of soil from site.

Tags: Lookahead

NOVEMBER 12 – NOVEMBER 17 LOOK AHEAD

Sunday, 11/12 through Thursday, 11/16 – 

NIGHT WORK: 9 PM – 5 AM SHIFTS

Set-up lane closures at 9pm. Minor utility street work along Congress, lanes will re-open each morning.

 

Monday, 11/13 through Friday, 11/17 – 

7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include removing guide walls and demoing slurry wall tops.

Tags: Lookahead