October 25 – December 21 look ahead

Thursday, 10/25 through Thursday, 12/20 – 

NIGHT WORK: M-TH – 9 PM TO 5 AM SHIFTS

Set-up lane closures at 9pm.  Work to include the installation of the buildings sewer line along Congress.  Lanes will re-open each morning.

 

Thursday, 10/25 through Friday 12/21 – 

1ST SHIFT: M-F – 7:00AM TO 3:30PM SHIFTS 

All work will be completed onsite.  Work to include structural steel, metal decking, concrete pours, interior detail work and window installation.

 

Thursday, 10/25 through Thursday 12/20 – 

2ND SHIFT: M-TH – 4:00PM TO 2:00AM SHIFTS 

All work will be completed onsite. Work to include the delivery and installation of precast panels.